Дмитрий Дуюнов: работы на производственных участках
24 April 2018
As of April 24 – finishing floor pouring operations are completed despite some difficulties with the service provider.
The rigging work aimed at moving and preliminary positioning of part of the equipment (compressor, receiver, nitrogen plant) is completed in the production area.
The equipment will be unpacked and mounted at the work stations after completing the positioning and upon fastening wiring ducts, a fire alarm system and lighting on the ceiling.
In the beginning of May there will be laser equipment in the production area.
By the end of the week it is planned to facilitate the storehouse for storing test hub motors.