Week results in Duyunov's project
Dmitriy Duyunov told about the key events of the first summer workweek at the traditional webinar on Thursday:
1) Signing the agreement with the technical supervisor and contractor responsible for the construction of "SovElMash" project at the Alabushevo site is planned for June 13. Now the specialists and employees responsible for these tasks are preparing the event.
2) The first motors developed by "SovElMash" are being prepared for production launch! Shaping the purhcase orders for size 90 IE3 class motors has started. The demand for these motors today is enough for utilizing the capacities of Zelenograd premises.
3) The laboratory equipment completed the calibration without any faults. The laboratory starts operating at full capacity next week. After that re-qualification will be held.
4) The equipment for checking the properties of electrical steel arrived (hardware and software system that is already assembled and mounted), now the team can fully control the quality of supplied steel.
5) The main scope of rough-in activities was completed in the new leased premises, final finishing started.
6) Siemens motors for testing are expected to be delivered.