The week results in the project "Duyunov's motors"
Dmitriy Duyunov tells what tasks the project team has completed this week.
While expecting the state registration of the land lease agreement, the team is conducting the scheduled activities connected with the beginning of construction at the "Alabushevo" site: the future centre project, the procedure for construction and orders, contractor companies.
The question of the enclosing structure for the construction site that complies with the requirements of the federal customs legislation, Moscow authorities and government of Russia is being considered.
The main assembly works have been completed in the winding area:
- electricity, gas, compressed air, nitrogen and lighting have been connected
- the equipment placement is near completion
- the Internet cable and video surveillance system have been installed.
According to the team's schedule, the winding area will start operating next week.
The new loading machine is placed on the foundation and fastened in the laboratory. The preparatory works for commissioning the machine start next week.