The week results for Duyunov's project
20 svibnja 2018
An overview video in which Dmitriy Duyunov tells about the last week events and also sums up the preliminary results of the first year of the project development.
This week the die casting machine has been delivered. The shaft alignment equipment is on its way, it has been hindering the start of motor testing and now its delivery is expected next week. In the new production premises the nitrogen plants, compressor equipment, chiller are being connected in order to start the main equipment in the shortest possible time (loading, casting machine and others).