Project news from Dmitriy Duyunov: project stage 4 plans
Dmitriy Duyunov told about the scope of work planned for project financing stage 4.
During this stage Duyunov's team intend:
- to conduct testing of 120 motor units and form specifications for the modernized and reengineered motor units;
- to complete equipment assembly for vacuum pressure casting site and subsequent launch of this site;
- to equip and start laser mechanical site (equipment for it is to arrive at the office in April or May this year);
- to organize the work of the robot-manned site (end of stage 4-beginning of stage 5 of project development)
- to tackle the subject of Alabushevo residence.
Currently the preliminary works are well underway in the testing laboratory, brief video reports about them can be found in our daily news in the official groups and on our YouTube channel.
At the moment various switching units, tooling and associated works are being provided for switching various motors to loading and torque measurement systems. New equipment is being studied, conditioning tasks for these units are being set, standard documentation is being prepared (in particular, testing programmes and methods, equipment list, diagrams, drawings). In other words, all the required conditions for further laboratory certification are established.
We are expecting a balancing machine to arrive in the near future.
The most difficult scope of work on self-leveling floor has already been dealt with, what is left is to accomplish it. And then facilitating the casting floor will start.
On Saturday,7 April, further talks on Alabushevo documentation take place.