Week results in Duyunov's project
Dmitriy Duyunov shares the top news of the past week. Apart from the equally important routine work, the following events can be emphasized:
1) The team started forming the committee on the laboratory qualification. As a result, the committee will perform the scope of preparatory works and conduct internal qualification by the beginning of February.
2) The new equipment required for completing the first orders in accordance with the signed agreements is being delivered to Zelenograd.
3) The practical arrangements concerning the project's lot at "Alabushevo" site are being dealt with.
On the SEZ "Technopolis "Moscow" map, lot 16 is still assigned to another company. The map will be updated as soon as the agreement with "SovElMash" is signed which will happen in the near future.
4) The work on testing motors and forming protocols that are already being translated into English continues.