At the last webinar Dmitriy Alexandrovich summed up the results of the ending work week which as usually appeared to be very busy.


The company introduced its technology on “Skolkovo” exhibition at the Startup Village event. We presented our “Kolobok” in size 318 mounted on «Version» chassis frame, with Curtis controller, and its prototype model – BLDC-motor Magic Pie by Goldenmotors company. All the event guests had an opportunity to test and compare both variants of the hub motor.

Follow the news not to miss the event videos!

Yesterday we got the signed agreements delivered to Zelenograd as well as the commitment letter concerning additional funding of the project in case there is a need for it.
These documents are the last link in the complete package of documents prepared by the company for entering the special economic zone Alabushevo.
All the requirements of the special economic zone representatives at the previous stages have been met, all comments have been dealt with, the materials submitted in order to apply for Alabushevo residency have been prepared. Besides, the additional materials are ready which offer new opportunities for the project in terms of training specialists, taking part in making science and method textbooks and preparing young well-qualified staff members in partnership with higher education institutions.


Meanwhile, the alignment work on the loading machine has been completed in the laboratory. No-load testing of 318-size “Kolobok” and the test determining the motor rated voltage and the correctness of selecting the calculated winding turns have been conducted.


In the mechanical area, the process of connecting the fire alarm system and reporting system is near completion.
The works on the equipment assembly and configuring the line from the nitrogen plant and air compressor to the casting floor and laboratory are being conducted.