The week results in Duyunov's project
21 tháng 4 2019
Dmitriy Alexandrovich told about the main events of the past week at the weekly project webinar.
Renders for the future design and engineering department (appendices to the pre-project specifications) were prepared that the general contractor and architects are currently using as a basis for developing the exterior and interior design of the future building.
We obtained the audit report that had run faultlessly for the company and proved that the company keeps records in accordance with the due process of law.
We held more first iteration tests for the re-designed 90-size motor. After three more iterations the required package of documents will be made.