The week results in the project "Duyunov's motors"
Dmitriy Duyunov summed up the results of the current week and told about the latest project events.
1) Submitting the land lease agreement on the SEZ territory for the state registration has been postponed until Monday. After passing the state registration and getting the certified extract from the Unified State Register of Immovable Property (tentatively on the first days of June), the launch of the first activities at the Alabushevo site will become possible.
2) Calibration of the laboratory equipment will end in the beginning of June. By the middle of June the laboratory should be working in its previous mode.
3) Development of procedures, methods and specifications for hub motors is underway, the main requirements for hub motors are being defined.
4) Work with the design documentation as well as the project of the building exterior for the future design and engineering department continues.
5) New equipment is arriving. The laser equipment that is intended for the workflow processes and will be used for producing the first pilot batch of general purpose industrial motors has been recently delivered. As Dmitriy Duyunov expects, the first size-90 motor will be ready for pilot batch launch by the beginning of August.