Project news from Dmitriy Duyunov
16 五月 2018
In the new production premises the connection of nitrogen plants, compressor equipment, chiller is underway in order to launch the main equipment in the shortest possible time (loading machine, casting machine and others). The process of connecting and starting these machines was hindered by the repair works.
As soon as the specialists complete the connection, we’ll start mounting the laser equipment required for making elements of magnet core and installing the robots as well as other works.
Today we are expecting the delivery of a vacuum die casting machine. The shaft alignment equipment has already arrived to Saint Petersburg, which means that by the end of the week it will be in Zelenograd.
When this equipment is delivered, the team will be able to start testing general purpose industrial and modernized motors of sizes from 56 to 100. And after that we’ll start testing hub motors.
Thus, if all of these tasks are successfully completed, the main goal of stage 4 will be achieved.
Thus, if all of these tasks are successfully completed, the main goal of stage 4 will be achieved.
About Alabushevo: on June 10 we are expecting the expert committee meeting for reviewing the projects to enter the special economic zone. The project team is properly prepared for this meeting.