Новости проекта от Дмитрия Дуюнова: события первой половины текущей недели
26 April 2018
We are buzzing with activity, but the scope of tasks doesn’t grow any smaller!
Some of the things that have been done in the first half of this week:
The task of preparing the floor is completed. The contractor company hasn’t corrected its mistakes, but since we have no time for waiting, the problem has been solved by our own efforts.
Thanks to completing the process of pouring the floor, we have started to move the equipment to the production premises.
The fasteners for electrical conduit, low power networks, power mains, fire alarm system, lighting have been mounted on the ceilings. Concurrently we have started to complete power cabinets in order to provide power distribution to the equipment.
We have brought the winding machine into operation and embarked upon the test runs. Very soon we will move from the tests to more targeted actions.
We have found out the dependence that will allow to increase the accuracy of determining the motor losses by means of applying mathematics and certain measuring methods. We have checked the mathematical tools and proved their accuracy supported by the calculations.
Out short-term plans include completing mounting all ceiling elements, sorting out and locating the equipment, starting to connect the equipment, preparing for receiving the next equipment batch.
Some of the things that have been done in the first half of this week:
The task of preparing the floor is completed. The contractor company hasn’t corrected its mistakes, but since we have no time for waiting, the problem has been solved by our own efforts.
Thanks to completing the process of pouring the floor, we have started to move the equipment to the production premises.
The fasteners for electrical conduit, low power networks, power mains, fire alarm system, lighting have been mounted on the ceilings. Concurrently we have started to complete power cabinets in order to provide power distribution to the equipment.
We have brought the winding machine into operation and embarked upon the test runs. Very soon we will move from the tests to more targeted actions.
We have found out the dependence that will allow to increase the accuracy of determining the motor losses by means of applying mathematics and certain measuring methods. We have checked the mathematical tools and proved their accuracy supported by the calculations.
Out short-term plans include completing mounting all ceiling elements, sorting out and locating the equipment, starting to connect the equipment, preparing for receiving the next equipment batch.