The week results in the project "Duyunov's motors"
9 dezembro 2018
Dmitriy Alexandrovich Duyunov shares the latest news and events of the project with the participants of the last webinar.
This week:
- the second batch of the equipment for the casting floor has arrived;
- the ventilation cleaning system for air recirculation has been mounted;
- the equipment for boosting the potential of the laboratory has been delivered;
- the order for extra equipment has been completed to increase the power of the test bench up to 100 kW (now it's limited to 10 kW);
- we have started the talks with the lessor of our office in Zelenograd concerning the increase of the space rented by "SovElMash";
- the meeting of the residents and candidates for residence with the authorities of SEZ "Technopolis Moscow" has taken place;
- a number of test protocols have been formed.
We have completed testing of the motors with standard and combined winding in the equal power and torque mode and testing of the motor with "Slavyanka" and standard motor under the increased power (0.55 kW motor was tested under the 0.75 kW load). The testing has shown that under the increased power the standard motor doesn't operate and can't maintain the set load whereas the motor with "Slavyanka" works and operates in its regular mode.
It was also shown that after modernization the motor had improved its energy performance up to IЕ2+ class.
After the testing finished, one of the motors was sent to an independent laboratory to confirm the obtained results.